3 yrsRenewal Period
0.25 hrsEst. Response Time
$171,100Annual Burden Cost
11,800+Est. Annual Responses

The Department of Defense published a notice in the Federal Register on May 4, 2026, announcing it seeks renewal of the information collection associated with DFARS 252.232-7015 — the Performance-Based Payments — Representation clause. The Office of Management and Budget (OMB) approval for this collection lapses periodically, and DoD's renewed request keeps the data-gathering mechanism intact for another three-year cycle under the Paperwork Reduction Act (PRA).

What DFARS 252.232-7015 Actually Does

Performance-based payments (PBPs) are the preferred method of contract financing for DoD when a contractor cannot use customary progress payments and the contract value justifies the administrative overhead. Unlike cost-based progress payments — which advance funds as a percentage of incurred costs — PBPs tie financing disbursements to measurable, objective performance events defined in the contract's Performance-Based Payments Schedule.

Before a contracting officer can authorize PBPs, the contractor must certify, via the 252.232-7015 representation, that its accounting system meets the standards required to properly track and report the contract's cost and performance data. Specifically, the clause requires the offeror to affirmatively represent whether it uses a cost accounting system that complies with FAR 52.215-2 requirements and whether it can track costs by contract line item number (CLIN).

Without a valid OMB control number, contracting officers cannot legally require contractors to complete this representation, effectively blocking access to PBP financing on new awards.

Burden Estimate and Compliance Impact

DoD's burden analysis accompanying the renewal request projects the following aggregate compliance load:

ParameterEstimateBasis
Annual respondents11,800Contracts with PBP financing provisions
Time per response0.25 hours (15 min)Certification review + signature
Total annual burden2,950 hoursRespondents × time per response
Loaded hourly rate~$58/hrDoD GS-equivalent estimate
Annual dollar burden~$171,100Total hours × hourly rate

These figures represent the administrative overhead imposed exclusively by the representation clause — not the underlying accounting system compliance costs, which are assumed to already exist as part of normal contractor operations.

Performance-Based Payments: A Contractor Financing Primer

PBPs represent a meaningful cash-flow advantage for prime contractors on large development and production programs. Because payments are tied to completion of defined work events rather than cost incurrence, contractors can negotiate front-loaded payment schedules if milestones are sequenced appropriately. The financing does not bear interest (unlike commercial loans), and PBPs are not considered contract debt unless the contractor fails to deliver the associated performance event.

DoD has pushed PBPs as preferred financing since the 1990s, arguing the mechanism aligns contractor incentives with performance outcomes rather than mere cost spending. In practice, adoption varies by program type: fixed-price development contracts are the most common vehicle, while cost-plus-award-fee and cost-plus-incentive-fee contracts typically use cost-based progress payments instead.

The PRA Renewal Cycle and What It Means Practically

The Paperwork Reduction Act requires federal agencies to obtain OMB clearance for any standardized information collection imposed on ten or more respondents. Clearances run for three years. When an approval lapses, the agency must publish a 60-day public comment notice in the Federal Register (as DoD did on May 4), then a 30-day final notice, before OMB issues a new control number.

During the gap between expiration and renewal, contracting officers are technically barred from requiring the representation. In practice, most contracting activity simply adjusts by deferring PBP-financed contract awards or adding a suspense condition pending OMB renewal — but the administrative friction is real and can delay program starts by weeks.

Industry associations occasionally submit comments during PRA renewal windows to push for burden reduction or clause simplification. The current 60-day comment window closes early July 2026.

Contractor Implications

For contractors currently bidding on programs with performance-based payment provisions:

  • Existing contracts are unaffected — the renewal pertains only to the information collection clearance, not the underlying DFARS clause itself. Contracts already incorporating 252.232-7015 continue to operate normally.
  • New solicitations with PBP financing clauses may include a note that the collection is under OMB renewal review; contracting officers typically proceed on the assumption renewal will be granted before award.
  • Accounting system readiness remains the substantive bar. The representation is the paperwork mechanism; actual eligibility depends on whether the contractor's system meets the underlying standards — a more demanding and expensive compliance requirement than the form itself.
  • Small businesses are the most likely segment to face eligibility questions: many lack the DCAA-compliant cost accounting systems that underpin the certification, effectively making PBPs inaccessible regardless of the clause's administrative status.

Comments on the renewal may be submitted through regulations.gov using the docket number published in the Federal Register notice.

Sources