Federal construction carries a requirement unrelated to the work itself: before a contractor breaks ground, it has to prove a third party will pay if the job goes wrong. FAR Part 28, published under FAC 2026-01 and effective March 13, 2026, sets the bid guarantees, the bonds and the thresholds that decide which protections apply. Contractors reading only the underlying statute end up with the wrong numbers.
Background
Private construction protects unpaid subcontractors and suppliers through mechanic's liens. That remedy does not exist on federal projects, because no one can lien government property. Congress substituted a bond. The Miller Act, at 40 U.S.C. 3131 through 3133, requires the prime on a federal construction contract above a stated dollar figure to furnish two instruments before performance begins.
The two do different jobs. The performance bond runs to the government and covers the cost of finishing the work if the prime defaults. The payment bond runs to everyone supplying labor or material, and it is the only collection mechanism a second-tier supplier has when the prime stops paying. Under 40 U.S.C. 3131(b), both must come from "a surety satisfactory to the officer awarding the contract."
Key Details
A third instrument comes earlier. The bid guarantee protects the government against a low bidder who wins, then refuses to sign or produce the bonds, forcing an award to the next bidder at a higher price. FAR 28.101-2 fixes it at "at least 20 percent of the bid price but shall not exceed $3 million."
FAR 28.102-1 requires performance and payment bonds under 40 U.S.C. chapter 31, subchapter III on construction contracts exceeding $150,000. FAR 28.102-2 sets the amounts: the performance bond equals "100 percent of the original contract price," plus 100 percent of any later increase. The payment bond carries the same figure and may never be written for less than the performance bond.
The statute is stricter in one respect. Under 40 U.S.C. 3131(b)(2), the payment bond equals the total amount payable under the contract unless the awarding officer finds, in a writing supported by specific findings, that such an amount is impractical — and even then it cannot fall below the performance bond.
Below that ceiling sits a middle tier many small builders miss. For contracts greater than $35,000 but not greater than $150,000, FAR 28.102-1 directs the contracting officer to "select two or more" payment protections instead of a conventional bond. The menu at FAR 28.102-1(b)(1): a payment bond, an irrevocable letter of credit, a tripartite escrow agreement, certificates of deposit, or a deposit of the securities listed at FAR 28.204-1 and 28.204-2.
Alternative protection generally runs to 100 percent of the original contract price plus increases, though FAR 28.102-2 lets the contracting officer set a lesser amount on a determination that it adequately protects the government. It must be in hand before the contractor gets a notice to proceed or starts work.
One waiver exists: the contracting officer may waive the bond requirement "for as much of the work as is to be performed in a foreign country upon finding that it is impracticable for the contractor to furnish such bond." The implementing clauses sit at FAR 28.102-3 — 52.228-15 above $150,000, 52.228-13 for the middle tier.
Where the Statute and the FAR Diverge
The raw U.S. Code says $100,000. FAR 28.102-1 says $150,000. Both are correct: the Miller Act figure at 40 U.S.C. 3131(b) is an acquisition-related threshold subject to statutory inflation adjustment, and the FAR implements the adjusted number. The same gap runs through the middle tier — 40 U.S.C. 3132 covers contracts "more than $25,000 and not more than $100,000," the FAR $35,000 to $150,000.
The Subcontractor Clock
Payment bond rights carry short deadlines, and 40 U.S.C. 3133 enforces them without sympathy. A party with a contract with a subcontractor but none with the prime — typically a sub-subcontractor or supplier — may sue on the bond only "on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made."
The outer limit is separate. Any action must be brought "no later than one year after the day on which the last of the labor was performed or material was supplied," in "the United States District Court for any district in which the contract was to be performed and executed, regardless of the amount in controversy."
When Sureties Say No
Bonding capacity, not competence, keeps most small firms off federal construction. SBA's Surety Bond Guarantee Program backstops the surety rather than the contractor. Per SBA, it guarantees 90 percent of the surety's losses on contracts up to $100,000 and on bonds for socially and economically disadvantaged, HUBZone, 8(a) and veteran-owned small businesses, and 80 percent on all other individual contracts.
Published terms: eligible contracts up to $9 million non-federal and $14 million federal, the higher figure available where a federal contracting officer certifies the guarantee is necessary for the firm to get a bond; a fee of 0.6 percent of the contract price for performance and payment bonds; and no fee for bid bond guarantees. Applicants must still qualify as small under SBA size standards and satisfy the surety's own credit, capacity and character requirements.
SBA runs two channels. Under Prior Approval, every application goes to SBA before the bond issues. Under the Preferred Surety Bond program, a qualifying surety may "issue, monitor, and service bonds without prior approval by SBA."
What It Means for Contractors
Price the bond before pricing the bid. On any construction solicitation above $150,000, a firm needs surety capacity covering 100 percent of the contract price twice over — performance and payment — plus a bid guarantee of at least 20 percent.
Read the tier before assuming a bond is required. A $90,000 award does not automatically demand one; the contracting officer picks two or more protections from the FAR 28.102-1(b)(1) menu, and a letter of credit or certificate of deposit may cost less than a bond a young firm cannot obtain.
For subcontractors and suppliers, the discipline is documentary. Record the exact date labor was last performed or material last supplied on every federal job, because both deadlines in 40 U.S.C. 3133 run from it, and missing the 90-day notice extinguishes the claim however legitimate the debt. Firms a surety turns down should work the SBA program through an authorized agent.
Sources
- FAR Part 28 — Bonds and Insurance | Acquisition.GOV
- FAR 28.102-1 General | Acquisition.GOV
- FAR 28.102-2 Amount Required | Acquisition.GOV
- 40 U.S.C. 3131–3133 — Bonds of Contractors of Public Buildings or Works
- Surety bonds | U.S. Small Business Administration
- Become an SBA surety partner | U.S. Small Business Administration