Shipyards that can lift and set a 600-long-ton missile module into a stealth destroyer's hull now have a shot at the last of the Navy's three Zumwalt-class hypersonic conversions. Naval Sea Systems Command (NAVSEA) wants industry input on the Conventional Prompt Strike (CPS) Depot Modernization Period for USS Michael Monsoor (DDG-1001), a 27-month job set to start in May 2028, Naval News reported. NAVSEA announced Nov. 17 that it will host an industry day in Washington, D.C., on Dec. 9 to assess shipyard capabilities and technical requirements for the work, which is scheduled to finish in August 2030.

"The U.S. Navy is preparing to begin a more than two-year overhaul of USS Michael Monsoor in 2028 as the third Zumwalt-class destroyer to receive the service’s new Conventional Prompt Strike hypersonic missile system," Naval News reporter Carter Johnston wrote. Michael Monsoor follows USS Zumwalt (DDG-1000) and USS Lyndon B. Johnson (DDG-1002), and its completion would give the Navy three CPS-armed destroyers.

Two RFIs, Two Deadlines Around the Dec. 9 Industry Day

NAVSEA has issued two requests for information, N00024-27-R-4443 and N00024-27-R-4444, according to The Defense News. Responses on the technical exchange are due Dec. 4, while responses to the heavy-lift installation inquiry are due Dec. 15. That puts the technical exchange deadline five days before the industry day and the heavy-lift deadline six days after it, so firms that answer the second request will have heard NAVSEA's presentation in Washington first.

The outlet summarized the core requirement bluntly: "The installation requires contractors with heavy-lift, shipyard engineering and precision installation experience." That narrows the field. A depot modernization of this scale is not a routine availability that any pier-side repair contractor can bid, and a separate heavy-lift inquiry suggests NAVSEA is treating the module installation as a distinct capability question rather than an afterthought folded into a general ship-repair package.

What Replaces the Two 155mm Advanced Gun Systems?

According to NAVSEA, the modernization will require "large-scale structural modifications" and compartment reconfiguration, mirroring the earlier CPS conversions, to accommodate the new payload modules and launch infrastructure, Naval News reported. The centerpiece is the removal of the ship's two 155mm Advanced Gun Systems. The Navy cancelled procurement of the guns' specialized ammunition over rising costs, leaving the weapons without their intended rounds, The Defense News noted.

In their place goes a Large Missile Vertical Launch System module weighing approximately 600 long tons and measuring 44 feet 7 inches by 20 feet 8 inches by 41 feet 1 inch, according to The Defense News. The module holds four large-diameter launch tubes. Each tube accommodates an Advanced Payload Module carrying three CPS missiles, for a total of 12 hypersonic missiles per ship.

Interesting Engineering reported that the module is intended to be prefabricated and must fit within the hull without distorting its existing structure, a challenge on a ship with the Zumwalt class's inward-sloping hull, where stability, weight distribution and access all complicate the work. The outlet also described how the missile leaves the ship: "A gas system ejects the missile from its tube before the rocket motors ignite, reducing the stresses on the ship."

CPS itself is a joint Navy and Army weapon that pairs a two-stage solid-fuel rocket booster with a Common Hypersonic Glide Body designed to exceed Mach 5. The Army is developing the same weapon for its ground-based Dark Eagle system. The missiles are planned for storage at Naval Weapons Station Yorktown, Virginia.

Advertisement

Computing, Power and Cooling Work Beyond the Launcher

The launcher is only part of the scope. The Navy plans a comprehensive modernization of the ship's Total Ship Computing Environment (TSCE), including new hardware and software, open-architecture improvements and the combat-system interfaces needed to integrate the hypersonic weapon into the destroyer's existing systems, per Naval News.

NAVSEA will also upgrade electrical power conversion and distribution, and install high-efficiency chilled-water cooling equipment to support the added electronic and launch-system loads, The Defense News reported. For bidders, that means the work spans hull and structural trades, electrical and thermal engineering, and combat-systems software integration, creating room for teaming arrangements and subcontracts under whichever yard leads the availability.

Schedule Slips and a Missile Supply Gap Hang Over the Monsoor Conversion

The two earlier conversions show how the program has moved. The Defense News reported that USS Zumwalt's CPS modernization at Ingalls Shipbuilding in Pascagoula, Mississippi, reached about 94% completion in January 2026, with the ship in sea trials and acceptance testing and operational capability projected for 2028–2029. Lyndon B. Johnson is receiving its launch system during final construction, with delivery scheduled for April 2027.

Advertisement

The outlet also reported that a July 2026 Government Accountability Office report found the overall conversion program about 24 months behind its original schedule, and that the first at-sea CPS flight test from a Zumwalt-class destroyer has shifted from 2025 to 2027. The Defense News put missile production at six to seven rounds a year, below the 12-per-year rate it said is required to stabilize inventories.

Interesting Engineering, citing the same July 2026 GAO report for the six-to-seven-missile annual figure, wrote that with each Zumwalt requiring twelve missiles, "it would take at least two years to fill the siloes of each," and noted that the Navy shares the underlying technology with the Army.

Once all three conversions are done, the Navy plans to relocate the destroyers to Pearl Harbor alongside guided-missile submarines as a modern "Battleship Row," Naval News reported. Michael Monsoor is currently based at Naval Base San Diego, according to The Defense News.

What It Means for Contractors

The Monsoor DMP is a defined, near-term opportunity with a fixed window: May 2028 to August 2030. Shipyards and installation specialists should answer the RFIs that match their strengths, with the technical exchange responses due Dec. 4 and the heavy-lift installation responses due Dec. 15, and plan to attend the Dec. 9 industry day in Washington.

Firms that cannot lead a 27-month depot availability may still have openings. The scope's electrical power distribution, chilled-water cooling and TSCE open-architecture work maps onto specialized subcontractor capabilities, and prime yards will likely want partners with precision rigging and heavy-lift experience for a module of roughly 600 long tons.

Contractors should also watch the program's risk signals. A two-year schedule slip on the conversion effort, a flight test pushed to 2027 and missile output at roughly half the needed rate all bear on how firmly the Navy can hold the 2028 start. Teams that can show schedule discipline and lessons drawn from the Zumwalt and Lyndon B. Johnson installations will likely have the strongest case if NAVSEA moves from industry outreach to a solicitation.