A contractor who sends the contracting officer an informal letter asking for extra costs can end up with no interest on the money owed and no fixed deadline for a government answer, while a contractor who instead certifies that same request as a Claim starts an interest clock, a statutory decision deadline, and personal exposure if the certification is wrong. The two look similar on paper — both ask the government to pay more or extend more time — but the Federal Acquisition Regulation treats them as entirely different instruments. A Request for Equitable Adjustment (REA) is a negotiation. A certified claim under the Contract Disputes Act is a legal demand with statutory consequences. Contractors who don't know which one they're filing routinely give up money, deadlines, or both.

When a $100,000 Letter Isn't a Claim Yet

FAR 2.101 defines a claim broadly: "Claim means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract." That definition would seem to cover almost any written request for more money. But the same section immediately narrows it for contractors above a specific dollar line: a written demand seeking more than $100,000 "is not a claim under 41 U.S.C. chapter 71, Contract Disputes, until certified as required by the statute." In practice, a contractor can write, sign, and submit a detailed cost proposal worth millions of dollars, and it legally is not a claim — no CDA deadlines, no interest, no appeal rights — until it carries the certification language required by FAR 33.207.

FAR 2.101 also excludes the ordinary paperwork of contract administration from claim status entirely: "A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim." A pay application isn't a claim just because it asks for money — it only becomes one if disputed, or if the government sits on it too long. That carve-out is why routine invoices don't trigger CDA machinery, but a contested REA sitting on a contracting officer's desk for months can be converted into one.

Why the Interest Clock Only Starts on a Certified Claim

The single biggest financial reason contractors eventually convert an REA into a certified claim is FAR 33.208. Under that provision, the government shall pay interest on a contractor's claim "from the date that— (1) The contracting officer receives the claim (certified if required by 33.207(a))" — not from when the underlying cost was incurred, and not from when informal negotiations began. An REA sitting in negotiation for a year earns the contractor nothing extra for that year of delay. A certified claim for the identical dollar amount, submitted on day one of that same dispute, earns interest at the Treasury rate for every day it goes unpaid. That asymmetry is deliberate: Congress built the interest requirement into the CDA to discourage agencies from dragging out certified claims, and the REA process — which predates the CDA and has no comparable teeth — was never given the same mechanism.

Certifying isn't free, though. FAR 33.207(c) requires the contractor to sign specific statutory language: "I certify that the claim is made in good faith; that the supporting data are accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable; and that I am duly authorized to certify the claim on behalf of the contractor." That signature has to come from someone with actual authority to bind the company, and a "defective certification" — altered language, or a signature from the wrong person — doesn't kill jurisdiction outright but must be fixed before a board or court can enter final judgment. A defective or bad-faith certification is also the hook the government uses to pursue False Claims Act liability, which is why counsel typically reviews certification language line by line before it goes out, even after the underlying cost data has already been negotiated informally through the REA process.

The Six-Year Window Nobody Watches Until It's Almost Closed

FAR 33.206(a) gives contractors a hard outer limit: claims "shall be submitted, in writing, to the contracting officer for a decision within 6 years after accrual of a claim," unless the contract sets a shorter period. That clock does not start when the contract closes out or when negotiations stall — it starts at "accrual," which FAR 33.201 defines as the date "when all events, that fix the alleged liability of either the Government or the contractor and permit assertion of the claim, were known or should have been known," even though "monetary damages need not have been incurred" yet. A contractor who spends four years negotiating an REA informally, gets nowhere, and only then certifies a formal claim has used up a third of that window without realizing it — and if the facts that "fixed liability" happened earlier than assumed, the remaining runway can be shorter still. The six-year limit doesn't apply to contracts awarded before October 1, 1995, but for anything more recent it is an absolute ceiling, no matter how cooperative negotiations appear.

What It Means for Contractors

The practical playbook most contracts attorneys use follows directly from these three FAR sections. Contractors negotiate cost or schedule impacts as an REA first, because it carries no certification exposure, no False Claims Act risk, and lets both sides adjust numbers informally without locking in a "sum certain." Only when negotiation stalls — or when the six-year accrual clock starts looking uncomfortably close — does the contractor convert the REA into a certified claim under FAR 33.207, deliberately trading informality for the interest accrual of FAR 33.208 and the CDA's formal decision and appeal rights. That conversion decision should never be made by whoever handles day-to-day contract administration; it needs sign-off from whoever signs the certification, because that person is personally representing the claim as accurate, complete, and made in good faith. Contractors should also track accrual dates, not contract end dates, since the "knew or should have known" standard can start the six-year clock well before a dispute looks like one. Waiting for a contracting officer to acknowledge a problem is not the same as waiting for the claim to accrue.