The administration's 250-foot arch at Memorial Circle could move from planning to construction as soon as next week, and taxpayers still have no official price for it. The National Capital Planning Commission votes Nov. 5 on final site and building plans. Federal money is already moving: a National Park Service contract worth up to $500,000 went to Portland design firm Otak in May, KGW reported from federal contracting records. Spending documents also show the National Endowment for the Humanities has reserved $15 million for the project. At the same time, two new lawsuits filed by governments could stop the work before ground is broken.

For contractors, the timing matters more than the price. No construction contract has been publicly awarded in the sources reviewed. The only award confirmed so far pays for environmental and design support, and the larger build-out depends on a planning vote and a federal judge who has said she will rule quickly.

Why There Is Still No Official Arch Price

The White House has not published a cost estimate. In June, AP reported via ARLnow: "A cost estimate for the arch is still being calculated, but a mix of taxpayer and private funds is expected to pay for it, according to a White House official, who spoke on condition of anonymity because the president has not publicly discussed the project’s cost."

The figure most often repeated, about $100 million or more, comes from press reporting and not from a federal budget document. ThePricer, which compiled the public numbers, labels it a "press estimate, not a signed contract or final federal budget."

Trump said last year that the arch could be paid for with private donations left over from the ballroom project, according to the AP report.

What the $15 Million NEH Set-Aside Covers

Federal spending-plan reporting cited by ThePricer shows the National Endowment for the Humanities reserved $15 million for the arch. That breaks down to $2 million in special-initiative funds and $13 million in matching grants.

The early site work carries a separate number. Emails reviewed by The Washington Post, as summarized by ThePricer, showed the Park Service estimated initial work at Memorial Circle at about $600,000. ThePricer says the final cost, other federal contributions, private donations and actual spending of the reserved funds are not yet settled.

What Otak's $500,000 Park Service Award Actually Buys

Otak, a Portland engineering and design firm, received the NPS award on May 21 to help clear environmental hurdles for the arch, according to KGW. The records show the work covers Memorial Circle, the traffic circle connecting Arlington Memorial Bridge to Arlington National Cemetery.

Advertisement

The award is smaller than its ceiling. KGW reported: "Records show only about $235,000 of the total award has been formally funded so far." The Park Service reduced the initial obligation by roughly $265,000 the day after the award, and KGW said it is unclear whether that reflects a change in scope or a routine funding adjustment. The contract's service code is general architecture and engineering, including landscaping and design. KGW said the exact scope of work is unclear, and a receptionist at Otak's Portland office referred its questions to the Park Service.

Can the Nov. 5 NCPC Vote Clear the Way for Construction?

The approval track has moved quickly. The Commission of Fine Arts approved the architectural design at a May 21 meeting, according to ThePricer. On July 9, NCPC "voted to approve preliminary site and building plans for the structure to be constructed at Memorial Circle," ABC News reported, after hearing from more than two dozen commenters, most of them opposed.

The final vote is set for Thursday, Nov. 5, at 1:00 p.m. ET in an online meeting, according to the National Trust for Historic Preservation, which is urging the public to comment. Written comments are due by noon ET on Nov. 4.

Advertisement

Planning documents cited by CBS News and summarized by ThePricer describe two 10-hour shifts a day, year-round, for two to three years. ThePricer also reported that Interior Secretary Doug Burgum said on Sept. 3 that excavation was expected to begin within two weeks. As of Oct. 31, the sources reviewed for this story do not confirm that ground has been broken.

Three Lawsuits Ask Whether Congress Must Sign Off

Vietnam War veterans and a historic preservationist sued in February, arguing the arch needs congressional authorization under the Commemorative Works Act. That case sits with U.S. District Judge Tanya Chutkan.

On Oct. 8, the Arlington County Board became the first government body to sue, filing in the Eastern District of Virginia with representation from Democracy Forward. The complaint criticizes the speed at which the project has moved without the full review process and states, as AP reported via PBS: "The National Park Service, the agency responsible for projects on national park land such as Memorial Circle, is proceeding full-speed toward ground-disturbing construction." White House spokesman Davis Ingle said the administration has been "fastidiously compliant with all procedural and legal requirements and are certain this meritless and dilatory lawsuit will be dismissed."

D.C. Attorney General Brian Schwalb and Virginia Attorney General Jay Jones then sued and asked for a temporary restraining order, according to Rolling Out. They argue the arch lacks required approval from Congress, nearly doubles the capital's 130-foot height limit and skipped mandatory reviews. Their case was linked to the veterans' suit, which sends it to Chutkan. At a hearing Friday, she questioned why the government's national security argument surfaced so late and said she would rule quickly. The Justice Department argues the opponents lack standing.

What It Means for Contractors

The only award confirmed so far is a partly funded environmental and design support contract. There is no public construction solicitation in the sources reviewed and no published cost baseline, so firms tracking the arch have no number to bid against yet. Two events will decide what comes next: the Nov. 5 NCPC vote and Chutkan's ruling on the restraining order. If both go the administration's way, work such as site preparation, excavation, stone cladding and traffic management at Memorial Circle could follow, and the 20-hour-a-day schedule in the planning documents suggests the timeline could be compressed. If Chutkan blocks the work, new obligations would likely slow, leaving the Otak award as the only confirmed contract.

The funding mix is also a risk. A $13 million matching-grant component ties federal dollars to private gifts, and any subcontractor pricing against this project should know which source is paying for which phase before signing on. Watch SAM.gov for any Park Service solicitation tied to Memorial Circle.

Sources