Four Border Patrol highway checkpoints in South Texas and Southern California are headed into design-build construction, and one Albuquerque contractor will handle all of them. U.S. Customs and Border Protection issued Southwest Valley Constructors Co four delivery orders worth a combined $283 million on Nov. 19, 2026, according to USAspending records for the Kingsville, Texas, order. The largest, at $111 million, covers a checkpoint in Kingsville; the others cover Indio/Salton City, California, Eagle Pass, Texas, and Carrizo Springs, Texas.

All four orders sit under a single parent vehicle: indefinite-delivery, indefinite-quantity contract 70B01C26D00000025, one slot in a CBP multiple-award design-build construction program with a $10 billion shared ceiling. The parent record shows zero dollars obligated, so these orders appear to be the first funded work on Southwest Valley's slot.

Where the $283M in Checkpoint Work Goes

The Kingsville order, 70B01C27F00000007, is the biggest of the four at $111,000,000. USAspending describes it as "DESIGN-BUILD A BORDER PATROL CHECKPOINT LOCATED IN KINGSVILLE, TX." The record shows the order signed Nov. 19, 2026, and last modified the following day.

The remaining three orders break down this way, according to the Indio order, the Eagle Pass order and the Carrizo Springs order:

  • Indio/Salton City, California (State Route 86): $68,000,000 under order 70B01C27F00000010.
  • Eagle Pass, Texas: $56,000,000 under order 70B01C27F00000008.
  • Carrizo Springs, Texas: $48,000,000 under order 70B01C27F00000009.

Together the four orders total $283 million. Every order carries the same performance window, from Nov. 19, 2026, through Sept. 1, 2029, which gives the contractor less than three years to move each project from design through construction. The records classify the work under the commercial and institutional building construction NAICS code rather than heavy civil or highway construction, a classification that points to facility buildings rather than roadwork as the core of the scope.

Three of the four sites sit in Texas, giving the program a clear South Texas concentration in this first round. The California order, identified in the records as a checkpoint on State Route 86 with Salton City listed as the place of performance, is the only one outside Texas.

How the $10B Shared-Ceiling IDIQ Works

The parent contract is not a standalone award. CBP's description in USAspending reads: "VENDOR 7 - DESIGN-BUILD (DB) CONSTRUCTION IDIQ AS PART OF A MULTIPLE AWARD IDIQ CONTRACT WHERE A CUMULATIVE CEILING OF $10B WILL BE SHARED AMONG ALL CONTRACT HOLDERS FOR PROJECTS THAT ARE AWARDED UNDER IT."

That language tells contractors two things. First, the "Vendor 7" label and the multiple-award structure indicate that Southwest Valley is one of several holders of parallel contracts under the same program. Second, the $10 billion figure is a ceiling that all holders draw down together, not a guaranteed amount for any one of them. Every dollar CBP places with Southwest Valley reduces the capacity left for the other vendors.

The parent contract runs from May 1, 2026, through May 10, 2031, and the record lists it as signed May 11, 2026. Its total obligation is zero dollars. That is standard for a multiple-award IDIQ: holders receive no obligated funds at award, and money flows only when the agency competes and issues individual task or delivery orders. The parent record shows the contract was awarded under a two-step solicitation that drew 22 offers, and lists CBP's Administration Facilities Training Contracting Division as the awarding office.

Advertisement

The four checkpoint orders came roughly six and a half months after the parent period began, making them the first funded work on this vendor's contract in the federal records.

Why Three of Four Orders Drew a Single Offer

The competition data stands out. USAspending lists each order as "FULL AND OPEN COMPETITION," the extent-competed code that carries over from the parent IDIQ, and the Kingsville record describes the order as subject to multiple-award fair opportunity. Yet only the Kingsville order drew two offers. The Eagle Pass, Carrizo Springs and Indio orders each drew one.

A single offer on a fair-opportunity order means other IDIQ holders either passed on the project or did not submit in time. The records do not say why. Possible factors include each firm's current workload, its regional footprint in Texas and California, bonding capacity on a combined $283 million in near-simultaneous work, and the risk profile of fixed-schedule design-build work.

Advertisement

For CBP, single-offer orders raise a pricing question, since the agency cannot benchmark the winning price against a competing bid on those three projects. The public records do not show how CBP evaluated price on the single-offer orders.

What It Means for Contractors

For the other holders of the CBP design-build IDIQ, these orders show what the program is buying now: Border Patrol checkpoint facilities, packaged as design-build work with a roughly 33-month delivery window. Firms that skipped these competitions should expect more of the same and should decide whether to staff up for checkpoint-type scopes in Texas and the Southwest.

The low offer counts also signal opportunity. When three of four orders draw a single bid, a holder that can mobilize quickly in South Texas or the California desert can compete against a thin field. Subcontractors, including design firms, MEP trades, site-work specialists and security systems integrators, should watch for Southwest Valley teaming outreach as the four projects move from design into construction.

The shared ceiling deserves attention too. With $283 million already placed against a single vendor's slot, the remaining capacity under the $10 billion cap shrinks. Holders tracking the program should follow obligations across all vendors to gauge how fast the ceiling is being consumed and whether CBP is concentrating work with a few firms.

Small businesses that do not hold a slot can still reach this work through subcontracting. The records list an individual subcontracting plan for these orders, and checkpoint projects require local trades, material suppliers and testing labs in each region.

What Comes Next on the Four Checkpoints

Design-build orders put design ahead of construction, so the first phase at each site will be design work before crews break ground. All four orders share the Sept. 1, 2029, completion date in the records, which means the contractor will likely run design and construction on the four sites in parallel rather than in sequence.

GovConFeed found no CBP press release on the four orders. Further modifications, funding actions or new delivery orders under contract 70B01C26D00000025 will appear in federal procurement records and USAspending as the agency places them.