Federal contractors have about two weeks to get their paperwork, cash and contracting-officer relationships in order before a possible government shutdown, and even a clean stopgap is likely to leave them operating under continuing-resolution limits until spring. The current continuing resolution expires after December 11, 2026, and law firm PilieroMazza warns in a Nov. 25 client alert that "Unless Congress enacts additional appropriations or another CR, a funding lapse would begin on December 12, 2026." The firm's checklist, paired with a Federal News Network interview with Professional Services Council President Stephanie Kostro, sketches the planning problem companies face over the holidays.

Lawmakers are discussing another stopgap, but PilieroMazza says negotiations remain complicated by disagreements over defense spending, including the administration's request for an additional $350 billion for the Pentagon, and funding for the ongoing conflict in Iran.

Why a December 12 Lapse Would Hit Contract Administration First

The firm lists the consequences contractors should expect at affected agencies: closed facilities and lost access to government personnel, systems or work sites; delays in solicitations, awards, modifications, approvals, inspections and contract administration; furloughs of government staff not doing excepted or otherwise funded work; and slower processing of invoices and payments, although some payment systems may keep running for funded activities.

One item tends to surprise companies. Contractual, statutory and protest deadlines keep running during a lapse unless the relevant tribunal, agency or contract says otherwise. A bid protest clock or a claim notice period does not pause because the agency on the other side has sent its workforce home.

PilieroMazza's first recommendation is to clear the backlog now: get deliverables approved, invoices paid and modifications issued before December 11. The firm adds that contractors should press on the same items after a shutdown ends, because the government will likely delay paying invoices.

Stop-Work Orders and the 30-Day Clock Under FAR 52.242-15

The most consequential advice concerns how work stops. The FAR does not spell out what contracting officers must do in a shutdown, so instructions can differ from contract to contract. The alert stresses timing: "It is important to remember that once a shutdown commences, the contracting officer may be furloughed and unavailable, so ideally, you should maintain close contact with your contracting officers for instructions in advance of the shutdown."

If a contract includes FAR 52.242-15, Stop-Work Order, the contracting officer may issue a stop-work order that can entitle the contractor to an equitable adjustment for increased costs. If a contracting officer orders work to stop, or gives unclear instructions when performance is impossible, PilieroMazza says the contractor should not keep working, since it might not be reimbursed for work done during a shutdown. Still, the firm writes, "it is imperative that you seek a directive to stop work from the contracting officer in writing."

The clause also carries a deadline that is easy to miss after a long lapse. According to the alert, "a contractor commonly must assert its right to an adjustment within 30 days after the end of the period of the work stoppage." If a stop-work order is not canceled and the work is terminated for convenience, stop-work and termination costs are recoverable under the termination clause, though the firm calls a shutdown-driven termination for convenience unusual absent extenuating circumstances.

Advertisement

Primes also need to manage their subcontractors. If the government orders a stoppage and a subcontractor keeps performing, the prime may owe the sub amounts it cannot recover from the government.

What Costs Can Be Recovered After a Shutdown?

PilieroMazza tells contractors to document every shutdown-related cost, including wind-down, ramp-up or acceleration of work, labor, consulting and attorneys' fees, along with every communication with contracting officers, employees, teaming partners and vendors. Shutdown expenses may generally be recoverable through the Stop-Work Order and Changes clauses where they appear in a contract, with the exception of backpay and consequential damages, which generally are not.

Mitigation matters because it weighs on whether an equitable adjustment is granted. The firm suggests reassigning employees to projects that must continue during a shutdown, encouraging vacation, or moving staff to non-billable work such as training, with furloughs or layoffs as a last resort. It also recommends checking cash reserves, delaying non-essential spending and prioritizing critical payments.

Advertisement

Why PSC Expects a CR Running to Late February or Early March 2027

Even if Congress avoids a lapse, Kostro expects contractors to live under a stopgap well into the new year. She told Federal News Network's Federal Drive on Nov. 24 that "The continuing resolution expires on December 11th" and that PSC is looking for Congress to pass a new CR extending into calendar 2027, telling listeners to "think maybe late February, possibly early March" for its end date.

That timing means the fiscal year will be about half over before full-year appropriations arrive, which Kostro said scrambles agency spend plans in a pattern seen repeatedly over the past decade. "Let's start talking about how to function more efficiently under a CR and what makes sense," she said, calling the situation "the new regular" for contractors.

The defense side adds a second layer of uncertainty. Host Terry Gerton framed the $350 billion reconciliation push as unlikely to clear the lame duck, and Kostro said Senate-side lawmakers are instead looking at folding some of its priorities into the full-year Pentagon bill at lower levels. She cited $9.4 billion against a $17 billion request for rapid large-scale scaling; $47.2 billion for munitions, minerals and industrial-base expansion; and 25 additional combat aircraft rather than the 53 sought through reconciliation on top of the 32 in the base request.

The type of money matters as much as the amount. Kostro said reconciliation dollars "function as multi-year mandatory style funding that is insulated from stopgap phrases, brief shutdowns, et cetera, but regular discretionary appropriations are subject to continuing resolution restrictions." Work that moves from reconciliation into the base bill loses that insulation and must be spent under the rules that govern annual appropriations.

What It Means for Contractors

The near-term task is administrative: before December 11, push pending approvals, invoices and modifications through, confirm which contracts carry the Stop-Work Order and Changes clauses, and line up written instructions from each contracting officer while they are still reachable. Contractors should track the 30-day adjustment window from the end of any stoppage and keep protest and claim deadlines on the calendar regardless of agency status.

The longer task is financial. Companies that expected reconciliation-funded work, particularly in munitions and aircraft, should model smaller quantities and shorter funding horizons, and plan cash flow on the assumption that discretionary funding stays under CR restrictions until late February or early March 2027. As Kostro put it, contractors are asking "how do they manage their cash flow, looking at a continuing resolution."