Immigration and Customs Enforcement has put billions of dollars into new detention sites without first settling what they would cost or what comes next. In a report released Nov. 19, the Government Accountability Office found that ICE bought 11 warehouses for about $1.07 billion, then scaled the initiative down and now plans to sell seven of them. The agency also paid about $2.2 billion for four existing detention facilities in July and August 2026, while the scope, time frames and estimated costs of further purchases remain undetermined.
The audit, GAO-27-108665, is titled "Immigration Detention: ICE Should Determine Cost Effectiveness of New Initiatives Before Continuing." Federal News Network picked it up in its Nov. 23 newscast, summarizing the finding bluntly: "Immigration and Customs Enforcement has spent billions on new detention facilities without evaluating the cost-effectiveness of those purchases."
How the $45 Billion Detention Appropriation Turned Into a Warehouse Reversal
ICE received the money in July 2025 through Public Law 119-21, commonly known as the One Big Beautiful Bill Act. The funds are available through fiscal year 2029. GAO said ICE used the appropriation both to maintain existing facilities and to launch an initiative to buy and renovate a collection of warehouses for use as new detention facilities.
That initiative did not hold. After acquiring the 11 warehouses, ICE "scaled down the initiative significantly," according to GAO, and plans to sell seven. Federal News Network described the move as ICE having "already reversed course" on facilities it purchased last year. The outlet reported that ICE has spent more than $3 billion on facilities since 2025.
The agency then bought finished facilities. The four existing detention centers it acquired over the summer cost about $2.2 billion combined. GAO reported that ICE has not determined what comes next: the scope, time frames and estimated costs for further acquisitions "remain undetermined."
Why GAO Says ICE's Detention Spending Plan Is Inflated
ICE's internal guidance requires it to update its spending plan for detention funding. GAO found the agency did not update the plan to reflect the shifting status of the warehouse initiative or other planned acquisitions. The consequence, in the auditors' words: "As a result, the spending plan includes an inflated estimate of planned obligations, which affects oversight efforts and ICE's ability to assess long-term budget needs."
That matters for anyone reading the plan as a demand signal. A spending plan that still counts obligations tied to warehouses ICE now intends to sell likely overstates the pipeline of renovation, outfitting and operations work, and GAO says the inflated figure complicates oversight of the money.
What ICE Pays per Detained Person, by Facility Type
GAO also examined day-to-day detention costs. ICE obligated about $2.8 billion for detention in fiscal year 2025, an increase of about 41 percent from the prior year, amid expanded enforcement activity.
Daily costs per detained noncitizen varied by facility type. The nine Federal Bureau of Prisons facilities ICE used charged a median daily rate of $180 per noncitizen, the highest of any facility type. Privately operated facilities had a median rate of $151. Facilities operated through agreements with the U.S. Marshals Service or with state and local governments ranged from $85 to $103. ICE officials told GAO that the services provided, the detention standards used and location also influence rates.
The study reviewed documentation on detention expansion efforts, spending plans and facility costs from October 2022 through various points in 2026. GAO interviewed headquarters and field officials at four ICE field offices, visited multiple existing and planned detention facilities, and also analyzed Department of Defense and Federal Emergency Management Agency costs for supporting immigration detention. A January 2025 executive order had directed DHS to increase efforts to detain people apprehended for immigration violations and to allocate all available resources for ICE detention, and ICE received significant funding in July 2025 to operate and expand facilities.
Invoice Reviewers Stretched Thin as 55 of 87 Positions Sit Open
The expansion has strained the staff who check the bills. GAO said ICE uses various processes to manage and oversee facility costs, but some were affected by the rapid expansion of new facilities. The workload of staff who provide oversight and validate invoices for these facilities "increased significantly," and ICE is working to fill 55 of the 87 allocated positions nationwide.
GAO also found that ICE did not manage its detention facility investments in accordance with DHS acquisition practices, which include the development of life-cycle cost estimates. The auditors framed the fix directly: "Developing such estimates before making further acquisitions would position ICE to better assess these investments, reduce potential waste, and help ensure the cost effective use of taxpayer dollars."
What It Means for Contractors
Detention operators, construction and renovation firms, and service vendors should watch whether ICE adopts the life-cycle cost estimates GAO says DHS acquisition practices call for. If it does, future purchases could see more analysis before commitment. That may add time between announcement and award, but it could also produce documented requirements that bidders can price against rather than shifting targets.
The warehouse reversal carries its own risk. Firms that staffed up for renovation work on the 11 sites may face a shrinking scope as seven head for sale, and any contracts tied to those buildings could be modified or ended. The sales themselves may draw interest from real estate buyers and from operators looking for convertible space.
The cost data gives private operators a benchmark. With privately run facilities at a $151 median daily rate against $180 at Bureau of Prisons sites and $85 to $103 under Marshals Service or state and local agreements, ICE has data it could use to press on price in future agreements. GAO notes that services provided, detention standards and location also influence rates, so the comparison is not like for like.
Invoice processing is a near-term pressure point. With ICE working to fill 55 of 87 oversight positions, vendors billing ICE should keep documentation tight and may see validation delays. Whether ICE turns to contractors to clear any backlog is not addressed in GAO's summary.
Finally, the inflated spending plan means planned obligation figures overstate what ICE is likely to buy. Business development teams sizing the market should discount planned obligations tied to the warehouse initiative until ICE updates its plan.