A 1940s earthfill dam in southwestern North Dakota is set for a multi-year seepage fix, and a Montana heavy-civil firm will do the work. The Interior Department's Bureau of Reclamation has awarded the Heart Butte Dam Safety Modification contract to NW Construction, Inc. of Bozeman, Montana, according to the USAspending record for contract 140RR027C0003. The contract obligates $49,123,167, and its base-and-all-options value is $53,047,927.
The record lists a start date of Nov. 23, 2026, a last-modified date of Nov. 25, and a period of performance running to June 30, 2030. Reclamation bought the work as a firm-fixed-price contract under full and open competition, using negotiated proposals. Two offers came in. The award carries NAICS code 237990, other heavy and civil engineering construction, and the place of performance is Elgin, in Grant County, North Dakota.
Why Heart Butte Dam Needs a Safety Fix
Heart Butte Dam sits on the Heart River and forms the principal feature of the Heart Butte Unit of the Pick-Sloan Missouri Basin Program, according to Reclamation's project page. The agency describes the structure as a zoned earthfill embankment with a structural height of 142 feet, built from 1948 to 1949. Its reservoir, Lake Tschida, provides irrigation, flood control, recreation, and fish and wildlife benefits, and releases from the dam serve roughly 7,766 irrigable acres.
The trouble runs back to construction. Reclamation says cracks developed in the three-foot-thick concrete outlet works conduit near the dam's centerline in 1949, and crews repaired them, with more chemical grouting in 1953. The agency reports no major incidents of seepage carrying embankment material until 2013.
On Jan. 25, 2013, a routine inspection found fine, gray sand deposits inside the spillway conduit. Investigators traced the sand to foundation material moving with seepage through a contraction joint near the dam's center axis. In March 2013, Reclamation covered the lower part of the joint with two layers of geotextile filter fabric held by a stainless-steel plate, a step it calls a temporary repair.
Years of drilling programs and risk analyses followed, leading to a Corrective Action Study meant to "identify and evaluate modification alternatives to reduce the risks of internal erosion potential failure modes associated with various seepage paths in the backfill and the sandstone foundation of the outlet works conduit."
The agency's own risk finding is blunt. The project page states that "the lack of an engineered filter contribute to the risk of dam failure," alongside persistent seepage into the conduit and in the relic river channel area. It concludes: "Currently, the risk of dam failure is at an unsatisfactory level, and corrective actions are needed to reduce the risk of dam failure."
What the $49.1 Million Will Build
Reclamation's preferred alternative pairs two standard approaches to seepage in embankment dams: cutoff elements that block seepage paths, and filtration elements that keep moving water from carrying soil with it. The plan also calls for chemical grouting of the conduit joints and void grouting of the foundation from inside the conduit. Reclamation says the scope is driven largely by the dam's single penetrating conduit layout and by the possible need for flood management operations while construction is under way.
The agency completed a Final Environmental Assessment and a Finding of No Significant Impact on Jan. 15, 2025, which cleared the environmental review step before procurement.
The contract record describes the work in plain terms: "DK HEART BUTTE DAM SAFETY MODIFICATION." The "DK" prefix likely refers to Reclamation's Dakotas Area Office, whose site hosts the project page. The award was placed through the Reclamation Contracting Activity under the Interior Department's Departmental Offices.
How the 2027-2030 Schedule Affects Lake Tschida
The award lands on the schedule Reclamation published in advance. The project page said procurement would take place in 2026, with the construction contract expected to be awarded later this year, and the USAspending start date of Nov. 23 is consistent with that.
"Construction is currently planned for 2027 through 2030," the project page states. That window lines up with the contract's June 30, 2030 end date.
The reservoir will feel the work midway through. Reclamation says "Lake Tschida will remain at normal elevations in 2026 and 2027, with drawdown scheduled for 2028 and 2029 to support safe construction conditions." The agency adds that it will provide additional public notification about reservoir operations as the project approaches. Irrigators, recreation users and local officials in Grant County should plan for those two drawdown seasons.
Two Bidders and a $3.9 Million Option Gap
The record shows two offers for a $49 million dam job, a narrow field for federal embankment remediation. Safety of Dams work combines deep foundation treatment, grouting inside the conduit, and earthwork under strict quality controls, which may limit the number of firms able to bid. The firm-fixed-price structure puts cost risk on NW Construction. That matters on a job where drilling programs have already shown the foundation geology to be complicated.
The gap between the $49,123,167 obligation and the $53,047,927 base-and-all-options value is $3,924,760, which leaves room for priced options. The record does not list what those options cover. Contractors should watch USAspending modifications on 140RR027C0003 over the coming months to see whether Reclamation exercises them.
What It Means for Contractors
The Heart Butte award shows Reclamation's Safety of Dams program moving from study to construction on a schedule it published early. Firms tracking Interior infrastructure spending can watch for the same sequence on other dams: a Corrective Action Study, then an environmental assessment and FONSI, then a procurement year, then a construction contract. When a project page publishes a procurement year, a solicitation on SAM.gov may follow.
Subcontracting is the near-term opportunity to watch. A filter-and-cutoff remediation with conduit grouting would plausibly call for specialty drilling and grouting crews, geotechnical instrumentation, aggregate and filter-material supply, dewatering, and erosion control, some of it within reach of Dakotas and Montana firms. The prime contractor's subcontracting needs ahead of the 2027 construction start are the place to ask.
The low bidder count matters too. With only two offers on a full and open competition, heavy-civil firms that can staff dam work may have room to compete on future Reclamation Safety of Dams solicitations in the Missouri Basin region. Firms that want in should study the Heart Butte environmental documents and contract record now, since later dam projects may follow a similar technical approach and contract structure.