NASA has picked the company that will build the reactor control hardware for its first nuclear-powered deep space mission, and it did so without a competition. A federal award record on USAspending shows that NASA Glenn Research Center signed definitive contract 80GRC027C0003 with Aitech Defense Systems Inc. of Chatsworth, California, on Nov. 13, 2026. The firm-fixed-price award obligates $15,381,506 for Reactor Control Box (RCB) hardware for the Space Reactor-1 (SR-1) Freedom mission.
The award runs one year, from Nov. 13, 2026 to Nov. 13, 2027. The record lists the extent competed as "NOT COMPETED" and the solicitation procedure as "ONLY ONE SOURCE." None of the sources reviewed for this story includes a NASA or company announcement of the award, so the federal procurement data is, for now, the public account of the deal.
What the $15.4 Million Reactor Control Box Award Covers
The contract description is short. It states that "THE CONTRACTOR SHALL DESIGN, FABRICATE, PROCURE, TEST, VERIFY, AND DOCUMENT THE REACTOR CONTROL BOX (RCB) HARDWARE FOR THE SR-1 FREEDOM MISSION IN ACCORDANCE WITH THE STATEMENT OF WORK AND OTHER CONTRACT ATTACHMENTS."
That scope covers the full hardware cycle, from design through verification and documentation, rather than a build-to-print order. The statement of work itself is not public, so the record does not say how many units Aitech will deliver, whether flight and qualification units are separate, or what interfaces the box must support.
The record classifies the purchase under NAICS 334111, Electronic Computer Manufacturing, and product service code 1675, Space Vehicle Components. It also marks the acquisition as "COMMERCIAL PRODUCTS/SERVICES," states that certified cost or pricing data was not obtained, and notes that no subcontracting plan was required. USAspending lists Aitech as a small business, and the award used no set-aside. The place of performance is Chatsworth, in Los Angeles County.
The award traces back to solicitation 80GRC026R00160001, and the record shows the notice was posted for public view. NASA received one offer.
Why NASA Went Sole Source Under FAR 6.302-1
The award cites FAR 6.302-1, the exception that lets an agency skip full and open competition when only one responsible source can meet its needs. USAspending codes the justification as "ONLY ONE SOURCE-OTHER (FAR 6.302-1 OTHER)." HigherGov's summary of the contract puts it plainly: "This Definitive Contract was awarded sole source to Aitech Defense Systems because the government believes that only one company can provide the product / service (FAR 6.302-1)."
The public record does not include the justification and approval document, so it does not explain why NASA concluded Aitech was the only viable supplier. No source reviewed for this story gives NASA's specific reasoning for this award.
How SR-1 Freedom's Nuclear Power Module Fits Together
NASA announced SR-1 Freedom at its "Ignition" event and described the mission in an Oct. 20, 2026 Glenn Research Center article. The agency wrote that SR-1 Freedom "will be the first spacecraft ever to demonstrate fission power beyond Earth orbit, traveling to Mars to deliver a science payload called SkyFall."
The spacecraft's nuclear power module sits at the end of its boom. NASA describes it as a reactor that generates heat through fission and a power conversion system that turns that heat into electricity for the spacecraft's systems and its electric propulsion. The mission will demonstrate nuclear electric propulsion in deep space.
Responsibility for the module is split among several partners. Sierra Lobo Inc. will provide the closed Brayton cycle power conversion system, with the work running under the Space Flight Systems Development and Operations Contract III that Glenn awarded in 2024. The Department of Energy's Idaho National Laboratory is designing and developing the fission reactor. NASA also says the reactor portion of SR-1 Freedom "will remain inactive until the spacecraft leaves Earth orbit."
NASA's October article does not mention Aitech or the Reactor Control Box. The connection between this contract and the nuclear power module comes from the award description, which ties the RCB hardware to the SR-1 Freedom mission. How the box interfaces with the INL reactor or the Sierra Lobo power conversion system is not described in any public document reviewed for this story.
A Late-2028 Launch Sets the Clock
NASA plans to launch SR-1 Freedom in late 2028. Once in flight, the spacecraft will carry SkyFall, a team of three Mars helicopters evolved from the Ingenuity design, which NASA says will collect scientific data, demonstrate exploration zones, and identify potential water sources.
The agency framed its recent contract moves as schedule protection. "These contract actions not only reduce technical risk and help us maintain momentum toward our 2028 launch, but they also strengthen collaboration across our partners," said Steve Sinacore, SR-1 Freedom program director, in the October article. That statement referred to the contract actions NASA announced at the time, not specifically to the Aitech award, which was signed about three and a half weeks later.
The RCB contract's one-year period of performance ends in November 2027, about a year before the planned late-2028 launch. That leaves time for integration and testing at the spacecraft level, assuming the hardware arrives on schedule.
What It Means for Contractors
SR-1 Freedom is moving from announcement into hardware buys, and Glenn Research Center is the contracting office on this award. The public record shows work reaching the program in different ways: an existing Glenn contract vehicle (Space Flight Systems Development and Operations Contract III, for Sierra Lobo's power conversion system), the Department of Energy's Idaho National Laboratory (for the reactor), and a standalone sole-source definitive contract (Aitech for the RCB). Firms aiming for SR-1 Freedom subsystems should watch Glenn's solicitation stream closely, since the RCB solicitation number, 80GRC026R00160001, suggests this purchase was solicited on its own.
The sole-source route matters for competitors. Because the justification relies on FAR 6.302-1, companies that believe they could have built the control box had their opening at the notice stage, when an agency typically publishes its intent to award without competition, if such a notice was posted. With the definitive contract signed, that window has closed for this item.
The award also shows that a small business can hold a direct prime role on a flagship NASA nuclear mission, outside of a set-aside. Aitech won the work as a small business with no set-aside applied, under a commercial item acquisition and a firm fixed price.
The fixed-price structure puts cost risk on the contractor for a design-and-build effort tied to a first-of-its-kind spacecraft. Subcontractors and parts suppliers working with Aitech on the RCB should expect schedule pressure that tracks the 2028 launch date NASA has set.
Finally, the documentation gap is worth tracking. The statement of work, the justification, and any modifications will tell bidders more about how NASA buys reactor control hardware than the current one-line description does. Any follow-on awards would likely appear in the same federal procurement data.