The protest that put the Trump administration's plan for legal representation of unaccompanied migrant children on hold is over. The Government Accountability Office has rejected Acacia Center for Justice's challenge to a sole-source contract the Department of Health and Human Services gave Our Rescue, a nonprofit based in Sandy, Utah. In a decision dated November 18, 2026, GAO found that HHS's Office of Refugee Resettlement (ORR) had a sound basis for skipping competition. The contract covers nationwide immigration legal representation for unaccompanied children, work that Acacia, a Washington, DC organization, had performed as the prior contractor.
GAO's conclusion was brief: "The protest is denied in part and dismissed in part." The decision (B-424748, B-424748.2, B-424748.3) does not give a contract value.
How ORR Used Urgency Authority to Pick Our Rescue
ORR made the award on August 7 under unusual-and-compelling-urgency authority. The decision cites Revolutionary Federal Acquisition Regulations (RFO) 6.103-2, "Unusual and Compelling Urgency," with 41 U.S.C. § 3304(a)(2) as the statutory basis. A GAO footnote says the RFO provision and FAR 6.302-2, the urgency exception contractors know from the old FAR, are "materially similar," so GAO treats its earlier decisions under the old provision as persuasive.
The contract can run up to 18 months: a six-month base period, two three-month option periods and a six-month option period. ORR can exercise the options if necessary until a competitive contract is awarded. Acacia filed its protest on August 17, ten days after the award. GAO's decision dates Acacia's receipt of the justification and approval for other than full and open competition to September 4.
The award has drawn political fire. Mother Jones reported in October that Our Rescue is "a nonprofit founded by a former ICE agent that had no experience representing immigrant kids in court." The magazine also reported that dozens of federal lawmakers signed a letter raising concerns about giving the work to "firms so plainly unqualified for the task." It added: "The Our Rescue deal was put on hold after the nonprofit Acacia Center for Justice filed a bid protest, whereupon the administration awarded another contract to the US Committee for Refugees and Immigrants."
Why GAO Kept the Protest Despite a Parallel Court Case
GAO first had to decide whether it could hear the case. Under its regulations, GAO will not decide a protest when the matter is in litigation before a court and the court's ruling could render GAO's decision academic. HHS argued that a pending case in the U.S. District Court for the Northern District of California could do that. GAO disagreed. That case, brought by Acacia's subcontractors, challenges the agency's cancellation of funding for legal representation and its resulting failure to fund it, while the protest challenges the sole-source award to Our Rescue. Because the two address different agency actions, GAO kept the protest.
Bid Protests, Not Poor Planning, Caused the Delay
Acacia's main argument was one that often wins in urgency cases: the agency caused its own emergency. Under the urgency exception, an agency cannot rely on urgency created by a lack of advance planning. Acacia said ORR started a competitive award in November 2025 but did not consider an interim bridge contract until July 2026, even though it knew a June 15 pre-award protest had triggered a stay of the competitive procurement.
GAO rejected that argument. Its digest states that "the sole-source award did not result from a lack of advanced procurement planning." The record showed that ORR had taken reasonable steps toward a competitive contract since November 2025, and that the delays were principally attributable to multiple successive rounds of bid protests against the terms of the competitive solicitation.
Is an 18-Month Sole-Source Contract Too Long?
Acacia also challenged the contract's length. It argued that a possible 18 months exceeds the time ORR needs to make a competitive award, and that a sole-source contract under urgency authority should last only as long as necessary to meet the urgent need and to let the agency compete the work.
GAO looked at how the contract is built rather than its maximum length. The base period is six months, and ORR can exercise options if necessary until a competitive award is in place. GAO weighed the contentious history of the procurement, which has generated three rounds of protests since the solicitation was issued in November 2025, and ORR's statutory and court-injunction obligations to keep representation going, and it was not persuaded. "Based on the record, we see no reason to find the potential length of the sole-source contract to be unreasonable," the decision states.
Timeliness Sinks the Challenge to Our Rescue's Experience
Acacia's second supplemental protest attacked the qualification issue that drew attention in Congress: whether Our Rescue has the relevant experience to do the work. GAO never reached the merits. It dismissed that ground as untimely. GAO reasoned that concerns about Our Rescue's qualifications should have been apparent to Acacia when it filed its initial protest, well before it received the justification on September 4. It also noted that plaintiffs in the district court case had raised Our Rescue's alleged lack of experience at least as early as August 20, citing public sources. Under GAO's rules, protests not based on solicitation improprieties must be filed within 10 days of when the protester knew or should have known the basis. Acacia's second supplemental protest, filed September 14, came too late.
GAO therefore did not rule on whether Our Rescue is qualified. The dismissal rests on procedure.
What It Means for Contractors
Incumbents challenging an urgency-based bridge contract should take three lessons from this decision.
- Protest delays can justify urgency. If bid protests stall a competitive procurement, the agency can point to those protests to show that it did not cause the emergency. Arguments about lack of planning work best when the record shows agency inaction, not litigation.
- Structure matters more than maximum length. A short base period with options exercised only if necessary until a competitive award will likely survive a duration challenge even if the total possible term is long. Protesters should look at whether the agency is actually moving toward competition, not only at the ceiling.
- File every ground early. Challenges to an awardee's capability based on information a protester already has must be filed within 10 days of when it knew or should have known the basis, not held for a later supplemental protest. GAO does not require a protester to wait for perfect knowledge before filing. Acacia's challenge to Our Rescue's experience failed on timing.
The decision also shows that GAO applies its familiar urgency framework to awards under the Revolutionary FAR provisions. For ORR, the ruling removes the protest from the Our Rescue contract. It does not settle the separate district court litigation or the questions lawmakers have raised about who should represent unaccompanied children in immigration court.