A contractor that misses the Armed Services Board of Contract Appeals deadline by even one hour loses its appeal, and the clock that counts is the one on the Board’s wall in Eastern Time. That is the lesson of the Board’s Oct. 22, 2026 dismissal of Texas Global Distribution LLC, ASBCA No. 64333, which threw out a challenge to an Air Force termination for cause because the notice of appeal landed on day 91. Administrative Judge David M. Marquez, writing for the Board on the Air Force’s motion to dismiss, also called out the contractor’s opposition brief for case citations that appear to have been fabricated by generative AI.
The appeal involved Contract No. FA4417-24-P-0035, which the Air Force awarded on March 28, 2024 for emergency response vehicles at Hurlburt Field, Florida. The Board dismissed the appeal with prejudice, and
How an Insurance Lapse Became a Termination for Cause
The dispute began after the Air Force exercised the contract’s first option period through Modification P00003 on April 11, 2025. A week later, Texas Global’s operations manager told the government the company could not renew the required vehicle insurance and asked that the contract be terminated “without cause.” After a show-cause notice on May 1, 2025, the company again asked that the contract “be terminated at no cost.”
Instead, the contracting officer emailed a signed termination notice on May 20, 2025. It cited the insurance failure under FAR 52.228-8, found the failure not excusable, and stated: “This is the final decision of the Contracting Officer.” The notice also laid out the contractor’s 90-day right to appeal to the Board. On May 29, 2025, the Air Force followed with Modification P00005, which formally terminated the contract for cause and de-obligated $30,000.00 from two CLINs.
Why the May 20 Email, Not Mod P00005, Started the 90-Day Clock
Texas Global argued that the May 20 email was not a contracting officer’s final decision and that its appeal was timely because it came within 90 days of Mod P00005. The Board rejected that argument. It found the notice met every element of FAR 33.211: it described the dispute, cited the pertinent contract term, summarized the circumstances and gave the contracting officer’s decision with rationale. It also used “the exact language required by FAR 33.211(a)(4)(v),” the Board wrote, and represented itself as the contracting officer’s “final decision.”
Because the notice was a valid final decision, the Board did not need to reach the modification. It pointed out that in a termination for cause, the 90-day period begins on receipt of the contracting officer’s decision to terminate, not on later paperwork confirming it.
On Time in Houston, Day 91 in Virginia
Counsel for Texas Global, Mohammad W. Ullah of Houston, emailed the notice of appeal late on Aug. 18, 2025. According to a Nov. 23, 2026 analysis by PilieroMazza, it was approximately 11:56 PM in Houston. The Board’s email server, in Eastern Time, logged receipt at 12:56 a.m. on Aug. 19, 2025, which was 91 days after the termination notice.
The Board measured timeliness by its own clock. It cited Board Rule 2(a)(3): “Filing occurs upon receipt by the Board’s email server.” It also relied on Free & Ben, Inc., ASBCA No. 56129, which based the timeliness of an electronic filing on the Board’s local time rather than the filer’s. Because the 90-day period is statutory under the Contract Disputes Act and cannot be waived by the Board, the Board held it lacked jurisdiction over the late appeal.
PilieroMazza called the ruling “the first ASBCA decision to unambiguously state that filings, and notices of appeal in particular, are filed when they are received in the Board’s time zone.”
Which Citations Did the Board Flag as AI Hallucinations?
The Board then turned to the brief itself. “Texas Global’s opposition cites various cases that either do not exist or do not stand for the propositions Texas Global asserts,” the Board wrote. Three examples stood out:
- Hensel Phelps Constr. Co., ASBCA No. 49204, 96-1 BCA ¶ 28,061. The Board called it “fictitious.” The reporter citation belongs to a Department of Transportation Board of Contract Appeals decision, Trident Indus. Prods. Corp., and the Board could not find any decision published under ASBCA No. 49204.
- Placeway Constr. Corp. v. United States. Texas Global quoted language that, according to the Board, is “nowhere found” in the Federal Circuit opinion.
- “EBA Ernest Bland Assocs., CBCA 6934.” The docket number actually belongs to JAF Supply, Inc. v. Department of Veterans Affairs, in which the Civilian Board of Contract Appeals found an appeal submitted 91 days after the contractor received the final decision untimely. That runs against the point Texas Global cited it to support.
The Board gave those citations no weight. It also found “blatant misstatements of fact.” The brief claimed the May 20 notice was unsigned, left out the final-decision language, and that the contracting officer apologized and re-sent a signed version dated May 27. The record showed the notice was signed and included the required FAR 33.211(a)(4)(v) language verbatim. The Board found no evidence of any apology or retransmission.
The decision does not impose a sanction. It points to the Board’s Use of AI Policy and its prior decision in Huffman Constr., ASBCA Nos. 62591, 62873. “While the Board does not prohibit parties from using AI to assist in drafting filings, the Board’s Use of AI Policy advises that ‘regardless of the means that a party uses to draft such filings, the party is responsible to ensure that they accurately reflect the facts and the law,’” the decision states. PilieroMazza noted the policy warns that parties may be subject “to appropriate sanctions if their filings mischaracterize the law, misquote cases, or cite to nonexistent cases.”
What It Means for Contractors
The decision gives contractors two concrete rules. First, a termination notice that carries the FAR 33.211 final-decision language starts the 90-day appeal clock the day it arrives, even if the notice says a confirming modification “will follow.”
Second, the filing day closes on the Board’s Eastern Time clock, wherever the contractor or its lawyer sits. A firm on the West Coast filing at 9:30 p.m. local time on day 90 is already late, because it is 12:30 a.m. Eastern. PilieroMazza advises calculating the deadline in the Board’s time zone, filing well before day 90 and confirming receipt, filing during normal business hours when the Recorder can confirm receipt if day 90 can’t be avoided, and keeping proof of transmission.
On AI, the Board’s message is that the tool is allowed but the filer owns the output. Here, the hallucinated cases had no effect on the outcome, since the appeal was already late. They did, however, put counsel’s errors into a written Board decision.