ScottMadden, Inc. will keep managing utilities privatization work at three military installations in Alaska where the Defense Logistics Agency administers utility contracts, after the Government Accountability Office rejected a rival's challenge to the award, ruling that the agency was free to pick the lower-priced firm even though the losing bidder had a stronger past-performance record. The decision closes out a protest that tested how much weight a contracting officer must give past performance when it collides with a nearly $2 million price gap.

The task order, issued under RFQ No. SP0600-26-Q-0810 through General Services Administration Federal Supply Schedule procedures, covers utilities privatization support services at three Alaska military installations where DLA administers existing utility services contracts. C.H. Guernsey & Company of Oklahoma City quoted $12,288,767 for the work. ScottMadden, of Raleigh, North Carolina, came in at $10,309,883 — roughly $2 million less — and won the task order in a best-value tradeoff despite an evaluation that rated Guernsey's past performance more highly. Guernsey filed a protest with GAO arguing the agency got the tradeoff wrong on three separate fronts, and GAO denied every one of them in a decision issued Aug. 12, 2026.

Why GAO Rejected the Staffing Risk Argument

Guernsey's central technical complaint was that DLA's evaluators understated the risk in ScottMadden's staffing and seniority approach — essentially arguing that ScottMadden's plan for who would do the work, and how experienced they'd be, should have counted against the company more heavily than it did. GAO found that the solicitation itself gave vendors latitude to structure their staffing approach as they saw fit, which meant DLA could not penalize ScottMadden simply for choosing a different staffing model than Guernsey's. The decision states that "our review of the record shows that DLA was aware of the relative merits of ScottMadden's proposed approach and assessed the approach reasonably." In other words, the agency had considered the staffing tradeoffs Guernsey flagged and made a defensible judgment call, not an oversight.

Guernsey's second argument attacked ScottMadden's past-performance references directly, contending they weren't sufficiently recent or relevant to the Alaska utilities work to support the rating DLA gave them. GAO's response leaned on a standard that shows up throughout its bid-protest case law: past-performance evaluation is a judgment call, not a formula, and GAO will not substitute its own view for the agency's absent a clear error. The decision puts it plainly: "The evaluation of past performance is, by its nature, subjective." That single line does much of the work in the ruling — it tells contractors that a disagreement over how relevant a reference contract was, without more, rarely moves GAO to overturn an award.

Advertisement

How a $2 Million Price Gap Beat a Stronger Past-Performance Edge

The most consequential argument was Guernsey's last one: that the source selection authority's tradeoff decision was unreasonable given Guernsey's edge in past performance. This is the argument that actually decides who keeps a contract when one vendor is cheaper and the other has the better track record — and it's the one most protesters lean on when price and quality point in different directions. GAO sided with DLA, finding that the source selection authority had reasonably weighed ScottMadden's roughly $2 million price advantage against Guernsey's stronger past-performance rating and documented that tradeoff. GAO's decision does not require agencies to pick the highest-rated vendor when a solicitation allows a best-value tradeoff; it requires only that the agency's reasoning be documented and rational. The overarching message from the decision applies well beyond this single task order: "An offeror's disagreement with an agency's evaluation judgments, without more, does not demonstrate that those evaluation judgments were unreasonable."

That sentence is the closest thing to a thesis statement in the ruling, and it's consistent with how GAO has approached best-value tradeoffs for years — protesters need to show the agency's reasoning was arbitrary or contrary to the solicitation's stated evaluation scheme, not simply that they would have reached a different conclusion. Guernsey's filing amounted to a request that GAO re-weigh the same evaluation record DLA had already weighed, and GAO consistently declines to do that kind of re-scoring.

What the Alaska Utilities Work Involves

Utilities privatization support contracts like this one help DLA manage the transfer of on-base utility systems — water, wastewater, electric, and similar infrastructure — to commercial or municipal operators at military installations, a process that involves technical assessments, negotiations, and long-term contract oversight. The RFQ covered that support work at three Alaska installations where DLA administers those contracts, a state where remote locations and extreme conditions add cost and complexity to utility system transfers that don't show up in lower-48 privatization deals. Guernsey and ScottMadden competed head-to-head for the task order, and the protest turned entirely on fine-grained evaluation judgments — staffing risk, past-performance recency, and the price-versus-rating tradeoff — rather than on either firm's basic eligibility to perform the work.

What It Means for Contractors

The decision reinforces a pattern that shows up repeatedly in GAO's bid-protest docket: a documented best-value tradeoff that explains why a price advantage outweighed a past-performance edge is very hard to overturn, even when the price gap and the performance gap both look meaningful on paper. Contractors bidding against an incumbent or a higher-rated competitor should not assume that a strong past-performance file guarantees an award, or that a protest citing that file will succeed, if the competing quote comes in meaningfully lower and the agency can show its work. For firms in the GSA Federal Supply Schedule task-order space specifically, the ruling is also a reminder that solicitations giving vendors flexibility in staffing approach can make a staffing-based protest ground difficult to win — GAO will generally defer to an agency's assessment of a competitor's staffing plan as long as the solicitation didn't dictate a specific structure. Bidders drafting technical proposals in this contracting lane should focus resources on making their price competitive rather than assuming a stronger past-performance rating alone will carry a tradeoff decision. Protesters, meanwhile, should treat GAO's repeated deference to agency past-performance judgments as a warning: a protest built primarily on "our record was better" arguments faces long odds unless it can point to a specific, documented evaluation error rather than a difference of opinion about how the evidence should have been weighed.